CONSTRUCTION OF E-763 HIGHWAY, SECTION: PRELJINA–POŽEGA, SUBSECTION IV OF 134+675 KM 142+012.31 KM, LUČANI INTERCHANGE

 

The works on subdivision IV included preparatory and earthworks: mechanical excavation of materials with loading and transport, subsoil preparation, construction of embankments and replacement of low load-bearing soil, slope topsoiling, wide excavation of materials.

In addition to works on the main route, construction was carried out on the de-leveled intersection and deviation number 4, which involved preparatory, earthworks, and drainage works (construction of drainage systems and ditches, installation of drain channels), as well as grading and compaction of the subgrade.

Gravel wedges were installed behind the end piers and cones on the M26 bridge and the overpass at the Lučani Interchange.